Activities

The aim of redeveloping Westersingel and Pier Panderstraat is to reduce the speed to 30 kilometres per hour. The driving lane will be narrower and the cycle lanes wider. Crossings at Molenstraat and Fonteinstraat will be improved. The existing trees are being replaced because they are not growing well. New trees will be planted on both sides of the street. Space will be kept on the quay for parking and more greenery. There will be a footpath on the quay under the trees and among the greenery along the city canal.

Replacement and reinforcement of sections of the quay wall

As well as the refurbishment, part of the quay wall will also be replaced and another part strengthened. This is necessary because on these sections the piles under the quay wall have been damaged. As a result, they are no longer strong enough to support the quay wall.

Finalised design

In March 2023, the local authority’s project group, together with 15 representatives from both streets (a sounding board group), started work on a design for the two streets. Three meetings with the focus group and several surveys culminated in a preliminary design.

This preliminary design for the redevelopment of Westersingel and Pier Panderstraat was presented to the district on 12 June 2024 in community building De Remise. The local authority finalised its design based on the comments of local residents.

Work schedule

From 3 March (Tesselschadestraat up to Vossepark):

  • Removing trees.
  • Tree planting
  • Installing bat poles (see the Bat Measures heading for more information).

From 10 March:

  • Start of work on the quay wall.

From 15 March:

  • Tree pruning (along the Westersingel quay).
  • Placing bat screen (along Plataan quay to Molenstraat).

Information meeting

We will start redeveloping the streets in May. Before that work begins, we will organise a walk-in event for the neighbourhood. Residents will be able to ask questions about the work, planning and possible inconvenience. You will shortly find more information about this meeting on our website.

Road closure

During the works, Pier Panderstraat and Westersingel will be completely closed. You will shortly find the diversion routes on our website.

 

Bat Measures

Measures will be taken during the works to protect the flight route of bats.

  • Temporary measures: Replacement flight routes with trees, bat poles and screens.
  • Permanent measures: Planting elms for a permanent flight route.
  • Ecological supervision: Log of findings from field visits.